According to the provisions of Article 72 para. (8) of the Electricity Law No. 164/2025 (Law No. 164/2025) “After obtaining connection permits for power plants with an installed capacity exceeding 200 kW or connection permits for energy storage installations with an injection capacity of 1 MW or more, the holders of such permits are obliged to submit to the system operator financial guarantees for the proper execution of the connection permits, in accordance with para. (4). The system operator shall cancel the issued connection permits if their holders fail to submit the financial guarantees for proper execution.”
According to ANRE Decision No. 277 of 30.05.2025 regarding financial guarantees for the proper execution of connection permits, the stages, deadlines, and procedure for submitting such guarantees were established, without imposing mandatory clauses on the content of the financial guarantees.
Based on the legal provisions of Article 1774 of the Civil Code, the bank guarantee for proper execution shall be submitted by the holder of the connection permit and shall include at least the following:
| No. | Document name | |
| 1 | Model bank guarantee for proper execution |
|